How to do a door hardware takeoff from a door schedule

Plumb Jamb · Updated

A door hardware takeoff turns two documents, the door schedule and the hardware schedule, into a count of every hinge, lockset, closer and stop on the job. Whether you furnish the hardware or only install it, you need that count: it drives your material price, your labor hours and your receiving check when the boxes show up. This is the method we would use on a small commercial job, such as a tenant improvement or clinic, with a few dozen openings.

What you need before you start

Gather four things:

  1. The door schedule. One row per opening, usually on the architectural sheets. It lists the opening number, location, door size, door and frame type, fire rating and the hardware set (also called a hardware group).
  2. The hardware schedule or sets. Each set lists the items that go on every opening that uses it. On public and larger private jobs this is often in or next to specification section 08 71 00.
  3. The specifications and addenda. Where the hardware schedule and the spec disagree, you need to know which one controls. Note the last addendum number you priced.
  4. The floor plans. You use these to confirm the opening count and to spot doors that are missing from the schedule.

Step 1: Build a clean door list

Type the door schedule into a spreadsheet, one row per opening. Keep the columns the schedule gives you: opening number, room, size, door type, frame type, fire rating, number of leaves (one for a single door, two for a pair), handing and hardware set.

Check the list against the plans. A common problem is a door on the plan that is not in the schedule, or a door in the schedule that is deleted by an addendum. Count the openings on the plans and compare the total with your list before you go further.

Step 2: Write out each hardware set once

For every set, enter one row per item: set ID, item, quantity per opening. A typical single office door might be:

Repeat the set ID on each row. Do not try to be clever and combine sets; if two sets differ by one item, they are two sets.

Pay attention to what the hardware schedule says about quantities. Many hardware schedules list quantities for a single leaf, and a pair of doors needs the leaf items doubled, while some items, such as a coordinator, a pair of flush bolts or an astragal, occur once per opening. Read the notes at the top of the hardware schedule for how the author counted.

Step 3: Count the openings that use each set

Now count how many rows in the door list use each set. In a spreadsheet this is one formula per set: a COUNTIF of the set ID over the hardware-set column of the door list. Doing this by hand on paper is fine too, but check yourself by adding the counts. The sum of openings across all sets must equal the number of openings on the schedule. If it is short, some doors have no set assigned. If it is long, you counted something twice.

Step 4: Multiply and roll up

For each item row in each set, multiply the quantity per opening by the number of openings using that set. Then add the totals for each distinct item across all sets. That gives you job-wide quantities such as 69 standard hinges, 6 non-removable-pin hinges and 8 office locksets (the totals from a 25-opening example job).

If your hinges come in different sizes or finishes (4.5 by 4.5 standard weight versus heavy weight, or non-removable pins on outswing exterior doors), keep them as separate items. Hardware suppliers will quote them differently, and you will want to see the difference when you receive the delivery.

Step 5: Check the rated openings

Fire-rated openings deserve their own pass. Filter the door list for any rating other than none and read the set for each one. In general, a rated opening needs to close and latch every time, so you expect to see a closer or another self-closing means, a latch, and often gasketing or smoke seals depending on the rating and the spec. The exact requirements depend on the opening, the code and the manufacturer's listing, so treat this check as a reminder to read the spec, not a code review. Note that a rated door can be self-closing through spring hinges instead of a closer, so a "no closer" flag is a question to answer, not always an error.

Also check pairs of rated doors for the extras they usually carry: coordinators, astragals, flush bolts and overlapping-leaf details.

Step 6: Look for what the schedule doesn't show

The schedule rarely tells the whole story. Look for:

Step 7: Decide whether you are pricing material, labor or both

On many commercial jobs a hardware distributor furnishes the finish hardware and the carpenter installs it. In that case your takeoff produces counts and labor hours rather than a material price. Keep your own labor numbers by item: how long a hinge, a lockset, an exit device and a closer take you, adjusted for the door material and the site. Numbers from a book or a spreadsheet are a starting point; your own tracked hours are better.

Step 8: Write down your assumptions

End the takeoff with two lists: what is included and what is excluded, and the questions you could not answer from the documents (the RFIs). A few that come up on almost every job: which addendum you priced through, who furnishes keying, who wires electrified hardware, and whether the hardware schedule or the spec controls where they conflict.

Doing it in a spreadsheet

You can do all of this with a few sheets and basic formulas. If you would rather not build it yourself, we made two versions. There is a free Door Schedule Starter with a door schedule, hardware-set counts and a check column that flags missing sets, undefined sets and rated doors without a closer: free download. For the full job, from item totals through pricing to a bid summary, there is the Door & Hardware Takeoff Workbook for $39 with a 14-day refund. Both work in Excel and Google Sheets. The layout and formulas were drafted with AI tools and then tested and corrected by us; the sample job is fictional, and the checks are bid-time reminders rather than a code review.

Whatever tool you use, the method is the same: one clean list, each set written once, counts that add up, and a hard look at the rated doors.

Frequently asked questions

What do I need before I start a door hardware takeoff?

The door schedule, the hardware schedule or sets (often in or next to specification section 08 71 00), the specifications and addenda, and the floor plans so you can confirm the opening count.

How do I know my hardware counts add up?

Count how many openings use each hardware set, then add those counts. The total must equal the number of openings on the schedule. If it is short, some doors have no set; if it is long, something was counted twice.

Does every fire-rated door need a closer?

In general a rated opening must close and latch, so you expect a closer or another self-closing means. Spring hinges can provide self-closing on some openings, so a missing closer is a question to answer from the spec, not always an error.

Do I price the hardware or only the installation?

It depends on the job. On many commercial jobs a hardware distributor furnishes the finish hardware and the carpenter installs it, so your takeoff produces counts and labor hours rather than a material price.