A good takeoff gives you quantities. A good bid letter tells the general contractor what those quantities do and do not cover. Disputes on door and hardware work rarely start with a hinge count; they start with who was supposed to wire the strike, who furnished the keys, or whether the work included overtime. This article gives you sample scope and exclusion language to adapt, plus twelve questions to send before bid day.

This is general information from a carpentry perspective, not legal advice. Have your own contract language reviewed for your business and state, and match your bid to the bid form you were given.

Why scope language matters

A bid is a number plus a description of what you will do for that number. If the description is silent, the other side reads it in their favor. Two habits help:

  1. State what you are including in plain, specific terms tied to the documents (door schedule, hardware sets, addenda).
  2. State what you are excluding, especially the items that are commonly argued about.

Sample inclusion language

Adapt these to your job and your trade:

Tie each line to a document where you can. "Per the hardware sets listed in the hardware schedule through Addendum 3" is better than "install all hardware".

Sample exclusion language

These are items that commonly belong to someone else. Include only the ones that apply, and make sure they fit your contract:

An exclusion only protects you if the reader sees it. Put your exclusions in the bid letter itself, not buried in an attachment, and repeat any exclusion that matters a great deal to the price.

Twelve questions to send before bid day

Questions sent early, in writing, create a record and often get the documents corrected. Send them as RFIs or as a short email to the estimator in charge. Number them so answers can be matched.

  1. Does the hardware set for each rated opening match the rating on the door schedule (closer, gasketing, latch)?
  2. Are the hardware functions in the specification (08 71 00) the same as the hardware schedule, and which controls if they differ?
  3. Who furnishes keying, cores and the keying schedule, and is a keying meeting required?
  4. Who provides power, wiring and conduit for electrified hardware, and who installs the strikes, operators and readers?
  5. Are frames shown as knock-down or welded, and are any frames to be installed in existing openings?
  6. Do any doors need an undercut, louver, vision kit or special prep not shown in the schedule?
  7. Who furnishes and installs thresholds, sweeps and weatherstripping at exterior doors?
  8. Are closers at accessible openings required to meet specific opening-force or clearance requirements called out in the documents?
  9. Who installs casework and countertops, and who furnishes blocking in the walls?
  10. Are toilet accessories and partitions furnished by the owner, the general contractor or this scope?
  11. Is any work required off-hours or in occupied space, and are there infection-control requirements?
  12. Which addenda are included in the takeoff, and what is the last addendum number?

How to use the answers

Keep a simple log: the number, the question, the date sent and the answer. When the answer is "see the specs" or silence, write your assumption into the bid and say so: "Bid assumes electrified hardware is furnished, powered and wired by others." If an answer changes your scope, send a short confirming note so the change is in writing.

Do not over-promise

Describe what you can verify. If a code or listing question is beyond your trade, say that you rely on the specifications and the architect's hardware schedule rather than certifying compliance. A bid is not the place to promise a code review.

Where this fits with the rest of your estimate

Scope and exclusions sit alongside quantities, labor hours, markup and overhead. If you keep them in separate documents, they drift apart; one fix is to keep the scope list with the takeoff and copy it into the bid letter at the end.

For a ready-made version, the Door & Hardware Takeoff Workbook ($39, 14-day refund) includes a Scope & Exclusions sheet with the inclusion and exclusion lines above (mark Y or N, then copy into your bid letter) and an RFI log with these twelve questions, alongside the door schedule, hardware sets, item totals and bid summary. There is also a free Door Schedule Starter if you only need the door schedule and checks: free download. We drafted the layout, formulas and text with AI tools, then tested and corrected them. The example data is fictional and the sheets are estimating aids, not legal or code advice.

Frequently asked questions

What should a door and hardware installation bid include?

A number plus a plain, specific description of what you will do for it, tied to the documents (door schedule, hardware sets, addenda), and a list of what you exclude, especially items that are commonly argued about.

Which questions should I send before bid day?

Questions on rated openings, which document controls, keying, electrified hardware wiring, frame types, special preps, thresholds and weatherstripping, accessibility hardware, blocking, accessories, off-hours work and the last addendum number.

What if the general contractor does not answer an RFI?

Write your assumption into the bid and say so, for example: "Bid assumes electrified hardware is furnished, powered and wired by others." If an answer changes your scope, send a short confirming note so the change is in writing.